SADDN

Antofagasta Region, Chile

We are constructing a desalination plant and a water collection and pumping system for Aguas Horizonte, which will supply desalinated water to three large mining operations in northern Chile.

  • 840

    liters/second current maximum desalination capacity

  • +160

    kilometers of 48" pipe

  • +3,000

    meters above sea level final altitude

Scroll

Aguas Horizonte Desalination Plant

The project will enable a reduction in the consumption of continental water used for mining production, one of the main commitments to sustainable development.

Key facts

  • March 2023

    Project beginning

  • +7,000

    people employed at the peak of construction, including in-house staff and contractors

  • 1.3

    kilometers of submarine pipeline with a diameter of 1.8 meters

  • 3

    pumping stations

  • 5

    220kV and 110kV substations

  • 2026

    Expected completion

  • March 2023

    Project beginning

  • +7,000

    people employed at the peak of construction, including in-house staff and contractors

  • 1.3

    kilometers of submarine pipeline with a diameter of 1.8 meters

  • 3

    pumping stations

  • 5

    220kV and 110kV substations

  • 2026

    Expected completion

Customer BOOT Aguas Horizonte
Scope of work EPC

Segment

Mining

To supply water to the Northern District, a reverse osmosis desalination plant is being built, along with a 160 km water collection and pumping system using 48" pipes, a 220 and 110 kV electrical transmission system, and a 25 km water distribution system for the mines.

The first pumping station will be located next to the plant, which will pump the water to a height of 1,100 meters. The second pumping station will raise the desalinated water another 800 m, and the last one another 1,300 m, until it reaches an industrial water reservoir with a capacity of 250,000 m3. From there, it will be distributed to two smaller reservoirs, one for the Radomiro Tomic processes and the other for the Chuquicamata and Ministro Hales processes.

Location

The project will operate near the municipalities of Tocopilla and María Elena (Tocopilla Province) and the municipality of Calama (Loa Province) in the Antofagasta Region in northern Chile.

  • Tocopilla

    Province

  • -22.0887

    Latitude

  • -70.1961

    Longitude

From the sea to the mountains

Discover the main milestones

  • Soil movement

    Soil movement was carried out where the desalination plant will be located, and the surface of the bilge, which is very uneven due to its topography with rocky outcrops, was optimally conditioned.

  • Platforms & temporary constructions

    The construction of the platforms and buildings where the first operators, supervisors, administrators, etc. were located was successfully completed, as well as other facilities such as dormitories, dining rooms, polyclinics and offices.

  • Opening of roads

    Work was carried out to open up the track for the laying of pipes, using heavy machinery for excavation and soil movement, and carrying out exhaustive and permanent monitoring using topographic drones.

  • Pipe transport

    One of the most complex tasks of the project was transporting the 9,000 pipes (almost 170 km) from India to Chile using seven ships. With the trenchers already in operation, the pipes began to be transported to the storage areas, before moving on to the bending phase.

  • Key components

    Once the civil works were completed, the first pieces of equipment were installed, such as multimedia filters and reverse osmosis trains. Centrifugal pumps, which arrived from Mexico, and electrical transformers for the pumping stations (the heart of the project) were also installed.

  • Electrical transmission system

    It is 14 kilometres long to supply the coastline and 19 kilometres for the mountainous area of the project, at 3,000 metres above sea level, making it one of the key points for desalination and water injection. A challenging task that has demonstrated the commitment of our multidisciplinary team and the incorporation of new technologies.

  • Marco Matranga · Sr. Project Manager

    “This is one of the most technically complex and important projects that Techint E&C has undertaken in its more than 70 years in Chile, and it has required each and every one of our employees to give their very best.”

Related projects

Next proyect

Dunkerque LNG