Buena Ventura Wind Farm

Gonzales Chaves, Buenos Aires

Built in just 15 months, it’s the Techint Group's first wind farm in the world.

  • 24

    wind turbines

  • 152,000 t

    less CO2 per year

  • 100 MW

    generation capacity

Scroll

Construction of the Buena Ventura Wind Farm

Once completed, the project will supply the equivalent of 50% of the electricity required by Tenaris's industrial center in Campana, Argentina.

Key facts

  • April 2022

    Start date

  • 500,000 m3

    of soil movement

  • 2,600 t

    of steel

  • 20,000 m3

    of poured concrete

  • 800,000

    labor hours

  • November 2023

    Completion date

  • April 2022

    Start date

  • 500,000 m3

    of soil movement

  • 2,600 t

    of steel

  • 20,000 m3

    of poured concrete

  • 800,000

    labor hours

  • November 2023

    Completion date

Customer Tenaris Argentina
Scope of work EPC

Segment

Energy transition

Due to the effective performance of our work teams and collaborative efforts across various sectors, the goals outlined with the customer were successfully achieved within the agreed-upon timeframe.

The project envisaged laying two different foundation configurations with diameters of 24 and 28 meters, defined according to the water table and the project’s proximity to channels and flood zones. The base of each turbine is set 3 meters deep into the ground. The 24 wind turbines were then mounted on the bases, comprising metal towers of 130 meters in height and blades measuring 75 meters in length.

Buena Ventura Wind Farm

The Techint Group’s first wind farm in the world

Location

Gonzales Chaves lies in a predominantly agricultural area in the Southeast of the province of Buenos Aires, 460 kilometers from the country's capital.

  • Adolfo Gonzales Chaves

    Buenos Aires, Argentina

  • -38.0324

    Latitude

  • -60.0994

    Longitude

  • Guillermo Mayayo · Project Manager

    “Since we started the construction of the farm, we encountered various challenges, but we also met many people from the area who demonstrated excellent learning capabilities and a willingness to work.”

  • Guillermina Micheli · Concrete Design Engineer

    “Working on this wind farm from the beginning has been a huge challenge and a great opportunity for me. It’s been a challenge because of the project’s size, and an opportunity because we were able to demonstrate what Techint E&C can build and achieve aims.”

  • Verónica Elorriaga · Planning Specialist

    “Although the schedule was tight, we were able to focus consistently on safety, the quality of work, environmental care and human quality, achieving our end objective.”