More news

The SADDN project enters its final stage with the construction of the reservoir at Radomiro Tomic

Published 18.3.2026

This new video shows the progress of this key infrastructure for storing and distributing desalinated water that will arrive from the coast to mining operations in the Northern District.

At 3,080 meters above sea level, on the premises of the Radomiro Tomic mine, the SADDN project team is moving forward with the final stage of construction of the reservoir that will store water from the desalination plant located on the coast. This infrastructure receives the flow from the drive line and distributes it to the facilities through a system of manifolds and pipes that surround the reservoir pool.

With most of the work already completed, the focus today is on the final details and maintaining strict operational discipline to complete the work safely.

Learn more about the reservoir in this video.

Related news

All the news